EC-3 Heat Power Plant
Construction phases since project inception in June 2007
November 2008:
October 2008:
starting August 2008:
June 2008 - September 2008:
June 2008 – July 2008:
May – October 2008:
May 2008 - September 2008:
May 2008 - July 2008:
March 2008 - October 2008:
January 2008- April 2008:
December 2007:
June 2007 - December 2007:
November 2008:
- connection to the public grid
- full load reached
October 2008:
- steam boilers at the EC3 power station put into operation
- cleaning works ("boiler blowdown") on the pressurized parts of both boilers successfully completed at the following parameters: pressure:
60 bar, temperature: 400 degrees Celcius, steam output: 60 t/h.
starting August 2008:
- assembly of the technological supply pipeline system and the Distributed Control System (DCS)
- assembly of the flue gas channels
June 2008 - September 2008:
- assembly of the flue gas dust removal system
June 2008 – July 2008:
- assembly of the flue gas - flue gas heat exchanger
May – October 2008:
- assembly of the slag and ash processing systems
May 2008 - September 2008:
- assembly of the turbo-generating set in the turbine house
May 2008 - July 2008:
- modernization of mechanical draft cooling tower
March 2008 - October 2008:
- assembly of the prefabricated constructional elements for the new boiler house
January 2008- April 2008:
- construction of the gypsum processing building
December 2007:
- The groundbreaking ceremony was held on December 12.
June 2007 - December 2007:
- demolition of the old boiler house
Blick auf das neue Kesselhaus mit zwei Rostkesseln vom Typ OR-45 und die Rauchgasreinigungsanlage
Abdampf-Kondensationsturbinensatz mit 14 MW Leistung im Maschinenhaus des Hauptgebäudes
Rauchgasentschwefelungsanlagen, Rauchgas-Wärmetauscher und Rauchgaskanäle