Mujada Small Hydropower Plant

 
 
Construction phases from project inception in October 2007 up till successful connection to the public grid in February 2009


April 2009:
  • official opening by German ambassador Joachim Schmidt
    and Waldemar Preussner


February 2009:
  • - connection to the public grid
  • - full load reached


December 2008:
  • completion of the intake
    construction work


September 2008:
  • completion of the generator and turbine installation work


August 2008:
  • construction of the intake
    (Tyrolean weir)


July 2008:
  • completion of exterior façade
  • supply of the electrical
    equipment


April 2008:
  • construction of the ground floor
    walls


January 2008:
  • laying the concrete foundations
    for the generator/turbine hall


November 2007:
  • supply of pipes and trenching
    works in preparation for the laying
    of the pipelines


October 2007:
  • clear-felling, start of construction works at the small hydropower
    plant in Bosnia and Herzegovina

Coordinates:
Google Maps:
44.067730, 17.35917 (intake)
44.080125, 17.369986 (engine house)
Google Earth:
44°04'04.51'' N, 17°21'33.04'' E (intake)
44°04'56.29'' N, 17°22'16.68'' E (engine house)