Building work on the Gradečka facility, PCC’s first small hydropower plant in North Macedonia, started in July 2012. Occasionally tough weather conditions and the rocky ground hampered the excavation work in particular. Nevertheless, the construction phase was successfully concluded just about one year later, with commercial electricity production commencing in August 2013.
Facility type: | Hydropower plant |
---|---|
Location: | Gradečka, North Macedonia |
CO2 reduction: | Average annual emissions reduction of approx. 3,504 metric tons CO2 |
Capacity: | 0.870 megawatts |
Generation: | around 3.75 million kWh electricity per year (multi-year average) |
Completion: | August 2013 |