The plant was commissioned in 2018. The construction period for the plant, with an annual capacity of 32,000 tons, totaled approximately three years, including a six-month delay.
The commissioning phase began on April 30, 2018, with the start-up of the first of the two electric arc furnaces. After the furnace vessel had been heated, the raw materials quartzite, coal, and wood chips were fed in the correct mixture. Once the raw materials had also been heated to approximately 2,000 degrees Celsius, the production of liquid silicon metal began. Official production, marked by the first tap, commenced on May 11, 2018. The second furnace was also started up on August 31, 2018.
On October 30, 2019, the Final Acceptance Certificate (FAC) was signed, and the plant was thus taken over for regular operation.
For further details relating to project progress and photos, please click here >>